Housing Grants, Construction and Regeneration Act HGRA
Contents |
[edit] Introduction
The Housing Grants, Construction and Regeneration Act 1996 (HGRA - also known as the Construction Act) is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly.
Provisions of the act include:
- The right to be paid in interim, periodic or stage payments.
- The right to be informed of the amount due, or any amounts to be withheld.
- The right to suspend performance for non-payment.
- The right to adjudication.
- Disallowing pay when paid clauses.
The Act applies to all contracts for 'construction operations' (including construction contracts and consultants' appointments). If contracts fail to comply with the act, then the Scheme for Construction Contracts applies.
[edit] 2011 amendments
The act was amended in October 2011 to close loop holes within its provisions.
The act now applies to construction contracts including those that are not in writing. Adjudication clauses must still be in writing, otherwise the scheme for construction contracts applies.
It is no longer allowable to define within a contract who should bear the cost of adjudication, and adjudicators have the right to correct errors in their decisions within 5 days of delivering that decision.
Specific changes have also been made regarding procedures for making payments:
- The dates for payments must be set out in the contract.
- The client (or specified person) must issue a payment notice within five days of the date for payment, even if no amount is due. Alternatively, if the contract allows, the contractor may make an application for payment, which is treated as if it is the payment notice.
- The client (or specified person) must issue a pay less notice (previously a withholding notice) if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
- The notified sum is payable by the final date for payment.
- If the client (or specified person) fails to issue a payment notice, the contractor may issue a default payment notice. The final date for payment is extended by the period between when the client should have issued a payment notice and when the contractor issued the default payment notice. If the client does not issue a pay less notice, they must pay the amount in the default payment notice.
- Pay when certified clauses are no longer allowed, and the release of retention cannot be prevented by conditions within another contract. So for example work contractors on a management contract project must have half of their retention released when their part of the works reach practical completion, not when the project as a whole reaches practical completion. This also applies to trade contractors on construction management contracts.
- There are also changes to the right to suspend work for non-payment or to suspend part of the works and to claim costs and expenses incurred and extension of time resulting from the suspension.
[edit] Retentions
The Construction (Retention Deposit Schemes) Bill 2017-19 proposes amending the Act to ensure that retentions are held in a third party trust.
For more information see: Retentions reform.
[edit] Related articles on Designing Buildings
- Adjudication.
- Arbitration.
- Causes of construction disputes.
- Collaborative practices.
- Common law.
- Construction contract.
- Construction (Retention Deposit Schemes) Bill 2017-19.
- Construction supply chain payment charter.
- Down payment chain.
- Egan report.
- Fair payment practices.
- Government construction strategy.
- Hybrid construction contract.
- Latham report.
- Local Democracy Economic Development Act 2009.
- Pay less notice.
- Payment schedule.
- Prompt payment code.
- Remedies for late payment.
- Scheme for Construction Contracts.
- The Late Payment of Commercial Debts Regulations 2013.
[edit] External references
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.